2026-07-31 03:19 UTC · 7d155dd

  • Mounting heights decided: 150 cm thermostat / 105 cm switch, measured at the center of the group; furniture-specific heights (110 / 90 / 85 / 70 cm) and one exception, kitchen 2.3's F 50 at 160 cm.
  • New positions to drill: kid's bedroom 17.2 and 17.3, Ekaterina's office 18.3, and a chill-zone wall group (IP66+, two boxes reserved); master suite revised — 14.1 drops to a single F 40, 13.3 gains a switch-height frame, 14.2 a Magnetic Charger.
  • LS ZERO rough-in verified: standard DIN 49073 boxes, but dedicated plastering frames — the finish must be frozen before plastering.
  • ComfoSpot rough-in: the six 230 V feeds are in place, wall cores still to drill; ordering spec and wall kits fixed. BBQ-zone counter reserved at two positions, 110 cm, IP44 minimum.
  • Control decisions: a custom per-unit module for the ComfoSpots (no Zehnder interface exists); 7 extractor fans, all with a KNX-side base; 12 warm-floor loops, the dressing room its own zone.
  • No scene is approved yet — Leave/Arrive included. Draft-wide: an open-items legend, "decided" as the default state of every fact, 3 new + 25 redrawn diagrams.